 |
| |
 |
 |
 |
COMMERCIAL
 |

|
 |
 |
 |
|
|
|
A.G. SPANOS
CORPORATE HEADQUARTERS
STOCKTON, CA
The A.G. Spanos headquarters building
in Stockton, California, is a six-story mid-rise structural steel frame
building, constructed over a concrete drilled pier foundation.
MatriScope
performed materials testing and inspections services for A.G. Spanos
headquarters building from the ground up. Our experienced team conducted
extensive field and shop welding and assembly inspections for the structural
steel, as well as earthwork and concrete inspections and testing.
| Owner: |
A.G. Spanos Companies |
| Contractor: |
HMH Builders, Inc. |
| Architect: |
Lesvosky Donaldson |
| Structural
Engineer: |
Showerman Hawn & Stone |
| Construction
Cost: |
$35 million |
|
|
 |
|
 |
|
|
|
|
TILESHOP
WAREHOUSE
BERKELEY, CA
The Tileshop Warehouse in Berkeley, California,
is a 24,000 square foot, two-story structural steel framed building,
constructed over a drilled pier concrete foundation. The building will
serve as the corporate headquarters for the TileShop.
MatriScope is performing
materials testing and special inspections services related to concrete,
structural steel, and fireproofing.
| Owner: |
Tileshop Warehouse |
| Contractor: |
ZCon Builders |
| Architect: |
VBN Architects |
| Structural
Engineer: |
Dominic Chu Structural Engineers |
| Construction
Cost: |
$15 million |
|
|
|
|
 |
|
|
|
|
CEMEX
CEMENT IMPORT TERMINAL
WEST SACRAMENTO, CA
The CEMEX Cement Import Terminal is a master-planned industrial effort located off of Industrial Boulevard in West Sacramento, California. This project encompassed various types and phases of reinforced concrete construction. At the completion of this unique project, there will be six 140 feet tall cement silos supported on a four foot thick pile and mat foundation. The concrete for the impressive silos was placed using slip form construction whereby the entire structure was poured monolithically. This challenging endeavor required staffing of eight MatriScope inspectors working two shifts around the clock for eight consecutive days.
MatriScope performed construction observation related to engineered fill
placement, structural concrete, masonry, and structural steel.
| Owner: |
CEMEX, Inc. c/o Industrial Consulting Resources |
| Contractor: |
Morton Contractors |
| Structural
Engineer: |
SEI Engineers, Inc. |
| Construction
Cost: |
$55 million |
|
|
|
|
 |
|
|
|
|
SACRAMENTO INTERNATIONAL JET CENTER
SACRAMENTO, CA
The Sacramento International Jet Center combines a 15,776 square foot, two-story office building and two 72,000 square foot hangar buildings. Building construction required the over-excavation of existing fill and re-compaction in order to achieve uniform building support. Buildings are pre-fabricated metal structures supported by conventional foundations with slab on-grade floor construction.
MatriScope was responsible for oversight of project delivery related to the initial geotechnical engineering report, earthwork observation and related laboratory testing services, and special inspections related earthwork, structural concrete, structural steel and high-strength bolting.
| Owner: |
Sacramento International Jet Center |
| Contractor: |
Sacramento International Jet Center |
| Architect: |
RMW Architecture & Interiors |
| Structural
Engineer: |
Neil O. Anderson |
| Construction
Cost: |
$10 million |
|
|
|
|
 |
|
|
|
|
|
|
|
|
|